Dear Cllr Goodway,
We believe that you as chair of PG take ultimate responsibility for the key financial issues being properly checked prior to signing the huge contract with Viridor.
The answers on two basic financial issues appear to be outstanding  
1. State Aid – the risk of the European Commission ruling the 25% WG subsidy to be illegal has not been accessed by Accounting officers
2. No updated Value-for-Money assessment has been made, neither by the Project or by the WG review.
You should be aware that the National Audit Office has just announced it is investigating three 25-yr incinerator contracts in England www.nao.org.uk/press-releases/defras-oversight-pfi-waste-projects/;
also that Defra withdrew WIC (waste infrastructure credits) last week for the Norfolk CC’s incinerator, putting Norfolk CC in trouble over their recent 25-yr contract  www.letsrecycle.com/news/latest-news/councils/defra-withdraws-ps169m-norfolk-efw-funding
You may have seen that EdF yesterday specified the State Aid issue as needing a decision before they sign the Hinkley Point nuclear deal.
We question that the Project officers are capable of giving appropriate advice on these issues and suggest appropriate independent experts should be consulted, eg. the WAO who are already considering the PG contract.
From Cardiff Against the Incinerator CATI 


Letter to Russell Goodway but no reply
Prosiect Gwyrdd contract with Viridor

Dear Cllr Goodway,
We believe that you as chair of PG take ultimate responsibility for the key financial issues being properly checked prior to signing the huge contract with Viridor.
The answers on two basic financial issues appear to be outstanding  
1. State Aid – the risk of the European Commission ruling the 25% WG subsidy to be illegal has not been accessed by Accounting officers
2. No updated Value-for-Money assessment has been made, neither by the Project or by the WG review.
You should be aware that the National Audit Office has just announced it is investigating three 25-yr incinerator contracts in England www.nao.org.uk/press-releases/defras-oversight-pfi-waste-projects/;
also that Defra withdrew WIC (waste infrastructure credits) last week for the Norfolk CC’s incinerator, putting Norfolk CC in trouble over their recent 25-yr contract  www.letsrecycle.com/news/latest-news/councils/defra-withdraws-ps169m-norfolk-efw-funding
You may have seen that EdF yesterday specified the State Aid issue as needing a decision before they sign the Hinkley Point nuclear deal.
We question that the Project officers are capable of giving appropriate advice on these issues and suggest appropriate independent experts should be consulted, eg. the WAO who are already considering the PG contract.
From Cardiff Against the Incinerator CATI 

No comments: